One of the most common questions GNX Development receives is: how long will it actually take? The honest answer is 10 to 16 weeks for most Central Florida pool projects, though factors like HOA approval, soil conditions, and permit office workload all affect the timeline. Here is what each phase actually looks like.
Full Pool Build Timeline in Florida
| Phase | Duration | What Happens |
|---|---|---|
| Design & proposal | Week 1-2 | Free consultation, site measurement, 3D rendering, proposal review |
| Contract & engineering | Week 2-3 | Signed contract, structural drawings, HOA submission if needed |
| Permit submission | Week 3-5 | GNX submits to the city or county. This is the most variable phase. |
| Permit approval | Week 5-9 | Orange County typically runs 3-5 weeks. Other counties may vary. |
| Excavation | Day 1-3 | Dig the hole. Typically done in 1-2 days by machine. |
| Plumbing & steel | Day 3-7 | Rebar cage and plumbing rough-in installed. |
| Gunite | Day 7-8 | Shotcrete shell applied. 28-day cure begins. |
| Tile & coping | Week 2-3 post-shell | Waterline tile and coping stone installed. |
| Deck | Week 3-4 post-shell | Travertine, pavers, or concrete deck installed around pool. |
| Equipment | Week 4-5 post-shell | Pump, filter, heater, salt system installed and plumbed. |
| Interior finish | Week 5-6 post-shell | Plaster, pebble finish, or glass tile applied. |
| Fill & startup | Week 6-7 post-shell | Pool is filled, chemistry balanced, equipment commissioned. |
| Final inspection | Week 7-8 post-shell | City or county inspector signs off. Certificate of completion issued. |
What Slows Things Down?
- HOA approval: Some communities require architectural committee approval before the county permit is submitted. This can add 2-4 weeks.
- Rain: Florida's rainy season (June-October) can delay excavation, gunite, and deck work.
- Permit office backlog: Peak construction season (January-May) often sees longer permit queues.
- Soil conditions: Rocky or high-water-table lots may require additional engineering and time.
- Change orders: Design changes after construction begins add time and cost.
What Speeds Things Up?
- Starting in September-December: Lower permit office volume and less rain.
- Having an HOA pre-approval process started before contracting.
- Using a licensed GC (like GNX) who manages all permits internally.
- Finalizing your design before signing. Changes after groundbreaking always add time.
Does GNX Handle Permits?
Yes, completely. GNX manages the entire permitting process with your local municipality. You make zero calls to the city. We submit, track, respond to comments, and notify you when the permit is approved. The permit phase is included in every GNX pool project at no additional charge.
Most GNX pool projects go from first consultation to swimming in 12 to 16 weeks total. We give you a realistic schedule upfront, not a best-case estimate.